Looking for Tenders

Article

InPower BC awarded John Hart project contract

0 64 Home

BC Hydro has signed a contract with InPower BC to construct an underground powerhouse at the John Hart Generating Station Replacement Project, located near Campbell River on Vancouver Island.

BC Hydro has signed a contract with InPower BC to construct an underground powerhouse at the John Hart Generating Station Replacement Project, located near Campbell River on Vancouver Island.

The new design will allow the average annual power generation to increase to 132.2 megawatts, from the existing 121 megawatts.

BC Hydro will continue to operate the existing station during the construction phase and will then transfer operations during the commissioning period to the new facility.

The estimated cost of the entire John Hart Generating Station Replacement Project is about $1.093 billion.

The project is estimated for completion by 2018.

JOC NEWS SERVICES

by Journal Of Commerce

Leave a comment

Or register to be able to comment.