LATEST NEWS
February 18, 2008
Construction Law
Contractors should benefit from new, less-ambiguous Waiver of Claims provisions in CCDC2
The Waiver of Claims provisions of the old CCDC2 have always been problematic.
The old clause provided a broad Waiver of Claims by the Owner except for those claims that the Owner had made in writing prior to Substantial Performance.
The only exceptions to that waiver were warranty claims, indemnification claims and claims with respect to “substantial defects and deficiencies.”
With respect to these latter claims, the limitation period was six years.
A difficulty with this provision from the Contractor’s perspective was that it was invariably amended by way of Supplementary General Conditions.
More generally, the provisions were unclear and consequently were rarely relied upon.
The new CCDC2 Waiver of Claims is far less ambiguous and includes some important amendments.
The new clause now limits the waiver and release of both the Owner and the Contractor to claims which they had knowledge of or “reasonably ought to have knowledge” of at the time of Substantial Performance.
If the Owner or Contractor does not have knowledge of the circumstances of a claim, and could not reasonably be expected to have such knowledge, there is no waiver or release.
This language is far more reasonable and in fact was frequently included in Supplementary General Conditions to the old version.
Claims for “substantial defects or deficiencies” are still released six years after Substantial Performance.
The waiver and release at the end of six years is “absolute” in the sense that it is not limited to claims that are known or reasonably ought to be known after the expiry of six years.
Claims for warranty work, or other work performed after Substantial Performance, are now released 395 calendar days after Substantial Performance.
The old CCDC2 did not include any definition of what was meant by a “claim made in writing” before the applicable period.
There were frequent disputes as to whether a particular communication was a “notice in writing” pursuant to these provisions.
It would thereby nullifying the release that otherwise would have occurred.
The new CCDC2 seeks to correct this problem by clearly delineating what must be included in a “Notice in Writing of claim.”
The notice must include:
1. A clear and unequivocal statement of the intention to claim;
2. A statement as to the nature of the claim and the grounds upon which the claim is based; and,
3. A statement of the estimated quantum of the claim.
Another problem that frequently arose under the old language was created by the link of waivers and releases to the final certificate for payment.
Under the old CCDC2, claims made in writing prior to the issuance of the final certificate were never waived or released.
In situations where a problem arose at the end of a project and the final certificate was withheld, there was an argument that there had been no waiver or release of any claims.
Under the new CCDC2, the trigger date for the release of claims is the sixth calendar day before the expiry of the lien period.
This provision provides greater certainly to the release date and ensures that claims are brought forward before the holdback is released.
Look for additional articles on other significant changes to the CCDC2 in upcoming editions of the Journal of Commerce.
Norm Streu and Chris Hirst are partners in the Construction & Engineering Group of the Vancouver law firm Alexander Holburn Beaudin & Lang LLP. Norm is a past chair of the Vancouver Regional Construction Association.
If you have any questions about this article, or any construction law related issue, please feel free to call Norm or Chris at (604) 484-1700.
| MOST POPULAR STORIES |
- Mobile-crane accident puts pedestrian in hospital
- Crane lands at Ledcor’s Shangri-La site
- Liberal “Green Shift” plan fails to address transit woes, industry officials say
- Enhance Energy plans to build commercial carbon-dioxide pipeline
- Bank of Canada’s interest-rate “hawks” begin to ascend
- 20 Most Popular Stories
| CURRENT STORIES |
- WorkSafeBC blames Canada Line crane death on lack of operator training
- Plan to certify B.C. crane operators continues
- Chinese construction market offers opportunities and risks to Canadian contractors
- Construction boom helps portable restroom businesses “clean up”
- TransCanada Corp. begins construction plans for $320-million Kibby wind-power project
- Saskatchewan’s skilled trades workers head home
- Construction association celebrates 50 years
| ALEX’S BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in Canada's economic environment. He also shares light-hearted reflections on life and current events.
Economics Blog More 
- China’s Reluctance to let the Yuan Rise – Learning from Japan (July 25, 2008)
- More on China and Japan – Similarities and Differences (July 24, 2008)
- A Higher Proportion of Homeownership, Mortgages and Condos (July 23, 2008)
Lifestyle Blog More 
- Doing the Economics Tango (July 21, 2008)
- Taking Somebody Else’s Child to the Cottage (July 14, 2008)
| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Saskatoon’s Circle Drive south-river bridge wins funding (Jul 24, 2008)
- Moose Jaw ready to select project manager for $61-million sports multiplex project (Jul 24, 2008)
- Peel Region makes green plans for new Heart Lake Community Recycling Centre (Jul 24, 2008)
- BMW Canada celebrates groundbreaking at site of new corporate headquarters (Jul 23, 2008)
- Thompson Rivers University receives funding for library, First Nations learning centre (Jul 21, 2008)
