A sunken concrete slab at an ice arena in Coquitlam was raised using a non-traditional technique called concrete lifting.
An arena ice surface is installed in a built space, which includes a slab of concrete, through which pipes run. The pipes carry a chilled fluid, which can lower the temperature of the slab so that water sprayed on top of the slab will freeze as a thin layer of ice.
The ice is built up to a thickness of one or two inches by repeated flows of water onto the surface
The concrete slabs underneath the rinks at the Coquitlam Planet Ice have sunk in certain sections, due to settlement of the ground upon which the structure was built.
A rink slab that has settled can become more expensive to operate, because it takes a greater amount of energy to freeze the thicker ice surface ice in the sunken areas.
The owner of the rink was searching for a solution to this situation and the traditional method of repair is to put in a new slab.
“I talked to four different contractors who repair concrete slabs in ice rinks and what they’ve done is busted out the slab and put in new concrete,” said Clive Clarke, client services representative with URETEK Canada Inc.
“We want to get the word out that ice rinks can be fixed using concrete lifting and don’t have to be busted out.”
The technology to lift concrete slabs has been around for many years.
Holes are drilled through the tilted concrete, and a cement mixture is pumped into these holes under pressure.
As the mixture begins to flow beneath the slab, it exerts pressure and raises the slab.
“We went in and drilled 690 small holes (5/8 inch), between the cooling pipes that run up and down the rink about four inches apart. Next we injected a polymer resin and brought the slab back to within a quarter inch of level.” said Clarke.
“The polyurethane is light weight, dense and adds extra insulation around the pipes. So this also makes the rink better.”
Clarke said the owners of Planet Ice also decided to lift the perimeter of the slab and the sidewalk outside of the building.
“The whole process took four days of work, from locating the lines, drilling, lifting and clean up. Busting out the slab and replacing it would take a month,” Clarke said. “Lifting the slab is about one third of the cost of replacing and repairing the slab.”
The project worked so well, that plans are already underway to lift the slabs in another rink at Planet Ice.
| MOST POPULAR STORIES |
- Sinkhole threatens Calgary building’s stability
- Highrise tool toss lands Calgary contractor in hot water
- Mike Holmes partners with First Nations on community-building pilot project
- Pine beetle spurs infrastructure construction in British Columbia
- City of Vancouver report slams botched demolition
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 372 projects with a total value of $3,335,585,749 that Reed Construction Data Building Reports reported on yesterday.
$1,200,000,000 Calgary AB Negotiated
$520,000,000 Grande Prairie AB Prebid
$75,000,000 Edmonton AB Negotiated
| CURRENT STORIES |
- Lack of local workers on Wuskwatim Dam project riles Manitoba union
- Roadwork continues in Burnaby, British Columbia
- Contractor default insurance catches on in Canada
- Construction firms learn to get ‘Bear Smart’
- Qualifications-based selection gains traction with Defence Construction Canada
- Hamilton ready to work with all general contractors, union-affiliated or not
- Worker survives crane rollover in Victoria
- Encana negotiates with China National Petroleum
- Rigger acquitted in New York crane collapse
- Work begins on Lynn Creek Rail Bridge project in Vancouver
- Archaeological assessments an integral part of pre-construction
- Outland Camps offers flexibility from coast to coast
- City of Vancouver report slams botched demolition
- VIDEO: Canada’s economy is slowing down
- Australian Labor government defends stimulus after allegations of political bias
- Western Construction wins contract for Bonnybrook Waste Treatment Facility
- Stimulus spending on U.S. national parks a major job creator
- Fences provide first line of defence
- Directional drilling less disruptive for locals
- Ontario Brownfield Act to change remediation rules next year
- High-tech surveillance protects construction sites from thieves
- Market grows for energy efficient construction trailers
- Site photographers focus on staying in the picture
- Fast Wrap asset protection firm coming to Canada
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canadian railway freight traffic on a better track (July 28, 2010)
- Waiting to see if the other shoe drops in Canada (July 16, 2010)
- Who wants Canada’s oil? (July 7, 2010)
- More