LATEST NEWS
Green Building | Heavy Equipment | Water & Wastewater | Trade Contracting | Steel | Building Envelope | Concrete
November 18, 2009
FLYNN CANADA
The green roof of Vancouver’s Convention Centre features slopes of up to 53 per cent.
Creating Vancouver Convention Centre’s green roof no simple task
Working atop a structure built on piles and at sometimes extreme angles made life interesting for the crews working on the Vancouver Convention Centre’s green roof.
The biggest living roof in Canada is surrounded by water on three sides, and the marine deck on which the building sits is supported by stilt-like piles.
It also features slopes of up to 53 per cent.
“There are no flat areas,” said Pete Taylor, a senior project manager with Flynn Canada, who oversaw the roof’s construction.
The idea was to integrate the project visually with the surrounding waterfront parkland and mountain backdrop, so that the entire vista appears as a single, crescent-shaped green-belt.
A host of cutting-edge environmental features, including on-site water treatment, deep seawater cooling and heating, and a giant skirt designed to help restore the local fish habitat have the convention centre seeing LEED Gold certification.
But it is the roof that is most visible and that has attracted the lion’s share of attention.
At 6.5 acres, it eclipses the National War Museum’s 2.6-acre green roof to rank as Canada’s biggest. It could hold 15 professional-size hockey rinks.
With more than 400,000 plants and grasses, featuring close to two dozen species native to the Pacific Northwest, the Vancouver roof is very much its own ecosystem.
It uses computers to detect leaks, and through a series of small channels and pipes, funnels excess rainwater for re-use in the washrooms.
The roof even has its own colony of European honeybees.
Work crews encountered no shortage of challenges in building all of this.
However, water was common to all of them.
First, there was the not-so-small matter of getting materials to the site. Access for heavy vehicles was limited to a single entrance on the one side where there was dry land.
“We were sometimes bringing in three to four dump trucks of growing media a day,” Taylor said.
“This was literally in the heart of the downtown, often in rush-hour traffic, and we had no room to park on-site.”
However, access paled in comparison to the structural issues.
Because much of the addition and roof jut out over the water’s edge like a large pier, crews had to find innovative ways to haul materials, including plants, liners, and more than 5,000 cubic metres of growing media, to the top.
And, with the building supported by piles, anything left on the roof had to be carefully and evenly distributed.
Crews had to use a hammerhead crane to reach the rooftop because the roadway at one end was the lone point of access.
“With a regular stick crane you can get the height, but you can’t get the reach,” Taylor said. “With a hammerhead, you can swing in about 120 feet over the roof.”
Working cranes from the water wasn’t an option.
“You’d have to put the crane on a barge, and the cost of doing that is astronomical,” he said.
As soon as crews got materials onto the roof, they had to immediately move them to specific locations using conveyors and lightweight buggies instead of heavy machinery, such as backhoes and bobcats.
The slopes proved particularly challenging.
Taylor said crews built diverters to protect soil and vegetation from Vancouver’s rainy climate.
Workers also laboured underneath rolling castor-style tents to keep materials dry.
Because of the slopes, some areas needed web-style retention systems, built using high-strength polymer matting and stainless steel cables, to hold the growing media, plants and 43 kilometres of drip irrigation piping in place.
Bruce Hemstock, of PWL Partnership, a Vancouver landscape architecture and consulting firm that worked on the project, said the roof portion of the job was one of the most technically challenging assignments his firm has taken on in its 35 years in the business.
“It was a very complicated project, yet we wanted to use simple and straightforward, off-the-shelf components,” he said.
“It was challenging to figure out how to make it all work.”
PWL needed to ensure the construction team could easily obtain materials such as roof drains rather than having them custom built.
“The whole drainage system on the roof was designed so it could be ordered from any manufacturer in Canada and installed on the roof without anything special happening to it,” Hemstock said.
With the various challenges addressed, project participants can focus on its benefits.
These include the stormwater management, and the lush, green exterior is able to curb the heat-island effect, which is typical with concrete and brick and is often blamed for localized warming.
As well, insulation from plants, waterproofing liner, six inches of growing medium, and four inches of extruded polystyrene increase natural temperature control and reduce the need for mechanical heating and cooling.
| MOST POPULAR STORIES |
- Olympic construction goes down to the wire
- Two more Fort McMurray projects moving forward
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Public-private partnerships working as intended, new report finds
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 350 projects with a total value of $6,260,468,758 that Reed Construction Data Building Reports reported on yesterday.
$1,000,000,000 Peace River RD BC Prebid
$500,000,000 Saanich BC Prebid
$500,000,000 Victoria BC Prebid
| CURRENT STORIES |
- New deal allows Canadian construction firms to bid on U.S. stimulus projects
- Construction continues on Canadian Natural Resource office in St. Albert, Alberta
- Canadian Construction Association summit zeroes in on industry concerns
- Art Gallery of Alberta addition showcases steel
- 5,000-room modular lodging project taking shape near Fort McMurray, Alberta
- Five-year forecast looking up for British Columbia construction industry
- Saskatchewan gets new natural gas trades training centre
- B.C. permit numbers rise while Alberta’s fall
- Trades lack LEED understanding
- Nexen, OPTI Canada get approval for cogeneration power plant near Fort McMurray
- Aecon wins $22 million in contracts for steam generators
- SNC-Lavalin partners with Russian bank to form engineering company
- Work continues on Pearl Condos in Toronto
- ‘A good first step forward,’ Canadian construction industry says of agreement
- Government should be more flexible with stimulus project deadline, outgoing ORBA president says
- Steel provides structure for historic hotel revival in Port Hope, Ontario
- Ontario businesses scramble to ready for arrival of HST
- Construction continues on Atira Women’s Resource Society housing project in Vancouver
- Five still unaccounted for after Connecticut power plant explosion
- U.S. manufacturing employment up, but construction losses continue
- Peterborough Utilities unveils plan for 10-megawatt wind farm
- China orders local governments to pay workers on private sites
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- A review of some global economic and policy expectations for 2010 (February 3, 2010)
- Synopsis of RCD’s webinar on the economic and construction outlooks (January 28, 2010)
- Increasing signs of world and U.S. economies getting back on track (January 28, 2010)
- More

| PROJECT NEWS BRIEFS |
Updates on Canadian construction projects from Reed Construction Data’s research team. More 
- Rounthwaite Dick & Hadley Architects begin work on arena plans for Flamborough, Ontario (Aug 17, 2009)
- Orillia Market Square aims for LEED Silver certification (Jun 25, 2009)
- Designs for new York Region District School Board building features energy efficiency (Jun 23, 2009)
- IPC Energy considers Milford location for future wind farm (May 22, 2009)
- Waterloo partnership seeks LEED Silver for West Side Family YMCA and District Library (May 22, 2009)



