December 21, 2009
With the Queen Elizabeth Way shut down, six machines completed the demolition in hours.
Demolition of Ontario bridge takes hours, not days
In the brave, new world of highway bridge demolition, projects are scheduled over hours, not days. The Martindale Bridge crossing the Queen Elizabeth Way (QEW) near St. Catharines, Ont. was no exception.
“We usually set some limits and allow contractors a specific number of hours to close the highway and get the work done,” said Ministry of Transportation spokesman Will Mackenzie. “In this case, we were scheduling 10 hours for demolition because of the wideness of the bridge.”
The overpass, constructed in 1939, once supported an intra-urban streetcar line that had long since gone out of service. The additional lane, running alongside the vehicle lane, was eventually devoted strictly to pedestrian and bicycle traffic.
“Because of that feature it was a unique bridge, but it didn’t have any particular historical significance,” said Mackenzie.
“After the streetcar line was taken out, the bridge still had that part of the deck.
“Today they would use continuous welded rail, but that wasn’t the case in the 1940s. Most of that type of rail bridge used what was essentially a viaduct filled with a gravel ballast and the track sections were laid on top of that. It allowed for a smoother track and was also easier for railway maintenance.”
The bridge was demolished to be replaced by a new span as part of a $183-million upgrade contract awarded to the Dufferin Construction Company to widen the QEW.
The contract represents the last remaining section between Toronto and Niagara Falls that has not been widened to six lanes.
“There simply wasn’t enough room to widen the highway underneath the bridge,” said Mackenzie.
“Originally, the contractor came to us with a plan to detour traffic around the abutment, but later they came to us and said they could do it faster and cheaper if we could close the highway for one night.”
A new single-span four-lane underpass structure was already under construction and ready to accept traffic as the old bridge was being demolished.
“The standard procedure is to begin by laying a foot-and-a-half to two feet of gravel on the highway to protect the existing road surface underneath from falling concrete and debris,” says Mackenzie.
Tonnes of cushioning material were laid down in the initial minutes of demolition. The contractor then sent in six excavators to attack the bridge simultaneously, as concrete was hammered to rubble and hydraulic cutters sheared steel rebar.
Backup units cleared away debris as the excavators progressed. In a few hours, the road was swept clean.
“The site was cleaned up and traffic resumed along the QEW at 10:00 a.m. on Sunday as scheduled,” said Mackenzie.
| MOST POPULAR STORIES |
- Sinkhole threatens Calgary building’s stability
- Highrise tool toss lands Calgary contractor in hot water
- Mike Holmes partners with First Nations on community-building pilot project
- Pine beetle spurs infrastructure construction in British Columbia
- City of Vancouver report slams botched demolition
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 372 projects with a total value of $3,335,585,749 that Reed Construction Data Building Reports reported on yesterday.
$1,200,000,000 Calgary AB Negotiated
$520,000,000 Grande Prairie AB Prebid
$75,000,000 Edmonton AB Negotiated
| CURRENT STORIES |
- Lack of local workers on Wuskwatim Dam project riles Manitoba union
- Roadwork continues in Burnaby, British Columbia
- Contractor default insurance catches on in Canada
- Construction firms learn to get ‘Bear Smart’
- Qualifications-based selection gains traction with Defence Construction Canada
- Hamilton ready to work with all general contractors, union-affiliated or not
- Worker survives crane rollover in Victoria
- Encana negotiates with China National Petroleum
- Rigger acquitted in New York crane collapse
- Work begins on Lynn Creek Rail Bridge project in Vancouver
- Archaeological assessments an integral part of pre-construction
- Outland Camps offers flexibility from coast to coast
- City of Vancouver report slams botched demolition
- VIDEO: Canada’s economy is slowing down
- Australian Labor government defends stimulus after allegations of political bias
- Western Construction wins contract for Bonnybrook Waste Treatment Facility
- Stimulus spending on U.S. national parks a major job creator
- Fences provide first line of defence
- Directional drilling less disruptive for locals
- Ontario Brownfield Act to change remediation rules next year
- High-tech surveillance protects construction sites from thieves
- Market grows for energy efficient construction trailers
- Site photographers focus on staying in the picture
- Fast Wrap asset protection firm coming to Canada
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canadian railway freight traffic on a better track (July 28, 2010)
- Waiting to see if the other shoe drops in Canada (July 16, 2010)
- Who wants Canada’s oil? (July 7, 2010)
- More