Public-private partnerships working as intended, new report finds
Public-private partnerships (P3s) for infrastructure projects are delivering savings in costs and time compared to conventional procurement approaches, according to a recent Conference Board of Canada report.
Early results indicate that most P3 projects are being delivered on or ahead of schedule, providing cost certainty to the public sector, noted Gilles Rhéaume, vice-president, public policy, at the Conference Board.
The multi-partner study, funded by agencies overseeing P3 projects, was launched to gather data on what is a relatively new project delivery method for Canada.
“Intuitively we thought it was working and protecting the public interest, but we wanted a new way to look at these questions,” said Steve Dyck, of Infrastructure Ontario.
Economist Mario Iacobacci’s report tracks the performance of P3 projects that reached financial close in 2004 or later under the direction of provincial P3 agencies or offices.
“We have a (seven year) experience that is growing in Canada, but no independent academic research had been done on this experience to date,” added Larry Blain, CEO of Partnerships BC.
The report notes advantages including life cycle costing, design innovation, construction cost control, performance-based contracts, avoiding deferred maintenance ensuring better building condition at hand-back.
Life-cycling costing and maintenance programs is one area where the P3 model excels, said Andy Manahan, executive director, Residential and Civil Construction Alliance of Ontario
“The public sector doesn’t always maintain infrastructure properly, but private sector operators have penalties for lack of performance,” he pointed out.
Recessions can cause different levels of government to cut back on infrastructure investment creating a problem of crumbling infrastructure at an “accelerated rate,” noted McGill University civil engineering professor Saeed Mirza.
“The first thing that goes during a recession is maintenance, which is reduced or eliminated.”
According to British Columbia’s Blain, the study corroborates what the P3 agencies always believed — their methodology is sound. The value for money test is the main tool used across Canada to determine whether a particular project is suitable for the P3 approach.
“Private sector finance has more cost than when the public sector borrows the money itself,” explained PPP Canada CEO John McBride.
“But, private sector finance brings discipline and due diligence. When private sector finance is at risk, you are sure they have thought through all the issues. If anything goes wrong it is to their account.”
Despite this fact, the study clearly states that the P3 approach is only appropriate in certain circumstances.
“The P3 method can deliver value, but this is not a silver bullet solution that can be used in every case,” said McBride.
Blain estimated that only 10-20 per cent of all capital projects taken on by the B.C. government could be done using the P3 method.
“The benefits of P3s tend to be truer on larger scale and more complex projects, not short-term and small projects,” said McBride.
“To attract bids it must be a larger project, because these projects require a lot of up front investment.”
| MOST POPULAR STORIES |
- High-tech oil sands project near Fort McMurray, Alberta could change industry
- TransCanada begins construction on British Columbia-Alberta pipeline
- VIDEO: B.C. Construction Association welcomes standardized contract forms
- Port Mann Bridge under construction
- Crane accident kills worker at construction site in Burnaby, British Columbia
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 263 projects with a total value of $8,919,878,049 that Reed Construction Data Building Reports reported on yesterday.
NATURAL GAS PROCESSING FACILITY
$500,000,000 Fort Nelson BC Prebid
$250,000,000 Fort Nelson BC Negotiated
$35,000,000 Winnipeg MB Prebid
| CURRENT STORIES |
- Crane operator certification deadline looms in British Columbia
- High-tech oil sands project near Fort McMurray, Alberta could change industry
- Saskatoon bridge closed indefinitely over structural concerns
- City of Regina project turns up all sorts of surprises
- Awareness about qualifications-based selection lacking: Survey
- Canadian Institute of Steel Construction launches Steel Day
- Saskatchewan bridge collapses, causing crane to topple
- Crane tips over, killing worker and injuring two
- Saskatoon man pulled from hole at construction site
- Churchill airport gets government cash for infrastructure upgrades
- Stantec acquires health care architectural firm
- Ground broken on Halifax RCMP headquarters
- Fanshawe College’s new Centre for Applied Transportation Technologies goes green
- Vanbots continues work on York University Life Sciences Building in Toronto
- Manitoba introduces new farm building code
- Heavy rains wash away bridges to Nova Scotia fishing village
- South Korea calls for financial safety net
- Jobsite safety a shared duty: Mechanical Contractors Association
- New technology could help find Jimmy Hoffa: Study
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canada’s construction starts in a transition phase (August 27, 2010)
- U.S. initial jobless claims rise to half a million again (August 19, 2010)
- It’s been 35 years since institutional construction starts as strong (August 6, 2010)
- More