LATEST NEWS
Water & Wastewater | Engineering | Heavy Equipment | Trade Contracting
February 17, 2010
Water and wastewater
Push underway to build First Nations infrastructure
A federal government plan to build 18 water and wastewater infrastructure projects in First Nations communities across Canada is well underway, with nine projects under construction and another five scheduled to commence by next month.
Funding for the projects totals $165 million with $75 million on the books for 2009-10. “The government is moving forward with all of the 18 water and wastewater projects and making progress,” said Margot Geduld of Indian and Northern Affairs Canada.
“For instance, construction for the Chateh Water Treatment Plant for Dene Tha’ First Nation in Alberta is well underway, with 35 per cent of construction to be completed by this year. This project is proceeding on budget and is ahead of schedule.”
Other projects under construction include:
• A new water intake piping system for the community of Natuashish, Labrador, which will supply water from a nearby river to a pumping station.
• A new mechanical sewage treatment plant in the Innu community of Sheshatshiu, Labrador.
• A new sludge system in the First Nation community of Wagmatcook, Nova Scotia, replacing the existing stabilization pond.
• Water treatment and reservoir capacity expansion in the Kahnawake First Nation in Quebec.
• A new sewage lagoon in the Black Lake First Nation, Saskatchewan.
Two Ontario projects form part of the federally-funded construction blitz.
Plans for construction of a $10-million water supply and treatment plant near Brantford are on the books for the Six Nations of the Grand River First Nation.
“The Six Nations water treatment plant is still in the early stages of planning,” said Geduld. “We’re expecting construction to begin in Fall 2010.”
Construction has already commenced on a $20-million water treatment plant for the community of Moose Deer Point First Nation, located about 30 kilometres south of Parry Sound.
The construction portion of the contract was awarded to Timmins-based Leo Alarie and Sons Ltd., a subsidiary of Aecon.
“The construction portion of the contracts is worth about $14 million,” said Greg Vaillancourt, division manager of engineered construction with Leo Alarie and Sons.
“We’re building a water treatment plant, elevated water storage tank, 10 kilometres of water main and four kilometres of water service over a fairly large area.”
The project will connect three parcels of land, which are separated by a wildlife nature reserve.
“The biggest challenge on the project is very tight access for construction of the water main,” said Vaillancourt.
“We’re working on very narrow rural roads and small residential roads and all of the excavation involves blasting. This contract involves drilling and blasting 30,000 cubic metres of rock, with the pipe trenches going down about eight feet.”
Winter weather has also been challenging.
“In December we got killed with 20 inches of snow in a single day,” he said.
“Although the ground is very wet, we’ve had a good January so we’re on schedule to complete construction by spring 2011.”
In 2006, the federal government identified 193 high-risk water systems in First Nations communities. That number has currently been reduced to 48.
“In addition, 21 communities were identified as priorities,” with water-quality and boil-water advisories, says Geduld.
“Today, after considerable construction activity, there are only four communities on that list.”
| MOST POPULAR STORIES |
- Sinkhole threatens Calgary building’s stability
- Highrise tool toss lands Calgary contractor in hot water
- Mike Holmes partners with First Nations on community-building pilot project
- Pine beetle spurs infrastructure construction in British Columbia
- City of Vancouver report slams botched demolition
- 20 Most Popular Stories
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 372 projects with a total value of $3,335,585,749 that Reed Construction Data Building Reports reported on yesterday.
$1,200,000,000 Calgary AB Negotiated
$520,000,000 Grande Prairie AB Prebid
$75,000,000 Edmonton AB Negotiated
| CURRENT STORIES |
- Lack of local workers on Wuskwatim Dam project riles Manitoba union
- Roadwork continues in Burnaby, British Columbia
- Contractor default insurance catches on in Canada
- Construction firms learn to get ‘Bear Smart’
- Qualifications-based selection gains traction with Defence Construction Canada
- Hamilton ready to work with all general contractors, union-affiliated or not
- Worker survives crane rollover in Victoria
- Encana negotiates with China National Petroleum
- Rigger acquitted in New York crane collapse
- Work begins on Lynn Creek Rail Bridge project in Vancouver
- Archaeological assessments an integral part of pre-construction
- Outland Camps offers flexibility from coast to coast
- City of Vancouver report slams botched demolition
- VIDEO: Canada’s economy is slowing down
- Australian Labor government defends stimulus after allegations of political bias
- Western Construction wins contract for Bonnybrook Waste Treatment Facility
- Stimulus spending on U.S. national parks a major job creator
- Fences provide first line of defence
- Directional drilling less disruptive for locals
- Ontario Brownfield Act to change remediation rules next year
- High-tech surveillance protects construction sites from thieves
- Market grows for energy efficient construction trailers
- Site photographers focus on staying in the picture
- Fast Wrap asset protection firm coming to Canada
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Canadian railway freight traffic on a better track (July 28, 2010)
- Waiting to see if the other shoe drops in Canada (July 16, 2010)
- Who wants Canada’s oil? (July 7, 2010)
- More