LATEST NEWS
November 29, 2010
Work finished on Trans-Canada Highway resurfacing in Manitoba
WINNIPEG
All four lanes of a 22 kilometre stretch of the Trans-Canada Highway in Manitoba were recently reopened as work was completed on a comprehensive resurfacing project.
The portion of highway, from Deacon’s Corner east of Winnipeg to the Highway 12 overpass at St. Anne, funnels traffic from Ontario and commuters from the south-eastern part of the province into Winnipeg.
CHRISTOPHER FRIESEN
Crews continue to work on safety upgrades to a 22 km section of the Trans-Canada highway that recently reopened after being resurfaced.”
Travel was down to two lanes during the past two summers, as crews worked to resurface the eastbound and westbound lanes in this $60 million dollar project, jointly funded by the federal and provincial governments.
In 2009, the eastbound lanes were removed and resurfaced with concrete.
This past summer, the westbound lanes along the same stretch were resurfaced with asphalt.
In the process, some older poured concrete culverts were removed and replaced with pre-cast culverts to improve drainage. Transitions onto rural roads were also upgraded and, in some cases, removed.
Ron Weatherburn is the executive director of construction and maintenance with Manitoba Infrastructure and Transportation.
He said that many factors went into determining what materials would be used for this stretch of road.
“Some of the things that are factors are the design life we are looking for,” he said.
“Concrete generally has a longer design life than asphalt does.”
Weatherburn said soil conditions, constructability and contractor availability all get evaluated, when deciding which material will be used and that, for Manitoba, that usually means asphalt.
“Asphalt is much, much more common for our department,” he said. “For the most part, we normally only use concrete in the Red River Valley (south of Winnipeg) because of the soil conditions. As well as this is where the concrete plants are.”
It may not be the only Manitoba highway to be surfaced with concrete, but Weatherburn said it is the most recent example.
He also said that resurfacing this eastern section of the Trans-Canada Highway with concrete offers his department a unique academic opportunity.
“It gives us a very good comparative test on how concrete compares to asphalt and how the price of concrete compares to asphalt for basically the same road,” he said.
Manitoba Infrastructure and Transportation had originally budgeted $63 million for this project, but came in under budget with a combined total cost of about $61 million.
The cost for the concrete lanes, Weatherburn said, was about $40 million.
While the asphalt lanes cost just more than $20 million.
However, he cautioned that while concrete does have a higher up-front cost, it isn’t double the cost as these numbers would suggest.
“It’s not completely comparable because we did a little more work last year, with some of the other transitions, that we didn’t have to do this year,” he said.
According to Manitoba Infrastructure numbers, 400,000 tonnes of aggregate and about 180,000 square meters of concrete were used in the eastbound lanes.
The westbound lanes required 580,000 tonnes of aggregate and 130,000 tonnes of asphalt.
Weatherburn said each material has advantages and disadvantages for road resurfacing.
Concrete lasts longer, but is more costly to repair, while asphalt is easier to maintain.
“It’s a fairly easy thing to mill off the very tip of it and put another asphalt layer on,” he said.
“Concrete, although it lasts a lot longer, once you need to go and re-do it, you normally can’t just put on an asphalt layer. You can’t mill it, so then you need to either fully reconstruct the lanes, if they are in that bad condition, or do major rehab work.”
Work on the project was carried out by two companies with the bulk of the resurfacing being handled by Mulder Construction and Materials Ltd.
Nelson River Construction Inc. handled the first 11 kilometres of construction along the eastbound lanes with Mulder winning the tenders to resurface the remaining 11 kilometres of concrete and the entire westbound lane with asphalt.
Weatherburn said that the sheer size of the concrete repaving job led to it being split into two separate tenders and that co-operation between the construction companies was necessary.
“We asked the contractors to work together to ensure that there was a proper transition,” he said.
Weatherburn added it will be 20 or 30 years before his department has a full understanding of how these concrete and asphalt surfaces compare.
Until then, motorists can enjoy a smoother, safer ride - in both directions – on this stretch of Manitoba highway.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 425 projects with a total value of $5,472,383,138 that Reed Construction Data Building Reports reported on Tuesday.
$60,000,000 Kelowna BC CANCELLED/ DEFERRED
WASTEWATER TREATMENT PLANT UPGRADES
$45,000,000 Grande Prairie AB Tenders
$30,000,000 West Vancouver BC Tenders
| CURRENT STORIES |
- High School Construction
- Victoria bridge inches closer to construction
- Collapse injures worker at Commonwealth Stadium
- Panel appointed to oversee hearings into B.C. mine project
- Bockstael celebrates 100 years
- More work needed to protect flaggers
- Co-founder of ATCO announces his intention to step down as chair
- SNC-Lavalin hit with $1.5 billion class action lawsuit
- PST returns to British Columbia
- Where does labour law stand on ladder safety?
- Construction continues on the MaRS Centre Phase II in Toronto
- Bending Lake Iron Ore pushes ahead with mining plans
- Reserve Properties continues plans for 109OZ condos in Toronto
- Ontario courts rule against owners rejecting low bids using undisclosed criteria
- Westray disaster 20th anniversary a call to safety action
- Dirt moves as Saskatchewan announces highway work
- Worker hurt in dressing room ceiling collapse at Edmonton stadium
- IBI Group raises $40.5 million from stock issue
- Plazacorp to spend $12.2 million on retail property development in 2012
- Ottawa to proceed with preliminary Lansdowne Park construction work, short-lists PCL, EllisDon and Pomerleau
- VIDEO: Highlights from the May 17 Daily Commercial News
- VIDEO: Common ladder safety errors in construction
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More









