LATEST NEWS
Heavy Equipment | Trade Contracting | Steel | Water & Wastewater | Engineering | Concrete
August 10, 2011
Segmental casings used more often
ANCHOR SHORINGS & CAISSONS LTD.
At the Union Station upgrade for Carillion Canada, Anchor Shoring, in a joint venture with Hayward Baker Inc., is installing nearly 900 micropiles using low-headroom equipment.
New technology is always on the horizon in shoring, a specialized industry with growing opportunities across Canada.
One of the keys to success in what has become a highly specialized industry is having the right equipment for the job at hand, said Dawn Tattle, president of Anchor Shoring & Caissons Ltd.
The company was the first in Ontario to import Bauer rigs from Europe.
The drill rigs twist 10 to 20-foot lengths of double wall casings into the ground and each segment is bolted onto the top of the next.
Segmental casings are becoming a more commonly used technique than vibrating liners into the ground, she said.
Typically, if the project is next to other buildings or below the water table, the company uses a caisson wall — a series of interlocking holes. If the ground is stable, the company uses a piling and lagging system, where piles are drilled and horizontal wood lagging is installed during excavation.
The demand for shoring on condominium and historical sites is on the rise in the Toronto area.
When maintaining historical buildings, there is more need for equipment that fits into a small area.
The company does a significant amount of work for expanding rail lines, which, along with many infrastructure projects, require noise and disruption to be minimized.
Excavations are also getting deeper and sites are getting smaller as people need more parking and land is at a premium, said Tattle.
“One of the complications is quality control and making sure the extra depth is accommodated for in the design,” she said. “The equipment has to be heavier and bigger.”
Anchor Shoring is currently installing 52,000 square feet of caisson wall around the perimeter of the X2 condominium site, along with about 222 tiebacks with a drilled length of 14,000 feet.
Tucker Highrise Construction, Inc. is the builder on the project and the shoring was designed by Isherwood Associates.
Drill depths for more than 300 interlocked vertical 1,000 mm diameter holes approach 90 feet, and drilling conditions are extremely challenging due to the depth of holes, the wet sand and gravel conditions and the proximity to nearby buildings and utilities.
About 7,000 m3 of caisson mix was required for the caisson wall.
Two Bauer BG-40 drill rigs were used, each providing 390 KNm of torque and the ability to drill holes up to three metres in diameter to a maximum drill depth of 80.5 metres.
“This equipment is able to install steel casings in tough ground conditions without the need to use a vibratory hammer,” said Tattle. “The casing can be advanced ahead of the drilling process.”
This is the method of choice in conditions, where it is necessary to drill adjacent to existing structures in areas of loose soil, or where vibratory methods can’t be used.
Sam Daaboul, project manager for Anchor Shoring, said the restricted access and traffic of the downtown location, the depth of the excavation and difficult soil conditions make it an exciting project.
The 22-metre excavation is next to existing streets, services and buildings and extends below the water table making drilling of the vertical holes and tiebacks challenging.
“The west end of the site will be braced by a waler strut system with the remaining sides braced by regroutable soil anchors,” he said. The walers and struts require 400,000 pounds of steel bracing.
The company is using much smaller equipment at the 90,000-square-foot Union Station upgrade for Carillion Canada.
In a joint venture with Hayward Baker Inc., Anchor Shoring is installing close to 900 9-1/2-inch diameter micropiles using special low-headroom equipment that can work in heights as small as 12 feet. Electric drill rigs maintain air quality in the congested areas with low ventilation.
The micropiles are drilled through fill overburden and into the rock. High strength steel bars are placed into the holes and grouted in place.
Due to the low headroom, the bars are placed in lengths as short as 10 feet and are connected in place to make the full length sections required using couplers.
“The total drill length for the job will be about 31,000 feet,” said Tattle. “Grout is mixed on site and we anticipate using over 16,000 bags of cement for the project.”
The micropiles are installed in four pile groupings around the existing columns.
Shoring posts are placed on each micropile and jacked, then the existing columns are removed.
A new footing and column are then installed.
Load testing was done in December 2010 with production drilling starting immediately after.
“We are also installing double corrosion protected (DCP) micropiles to support future walls of the structure,” said Tattle.
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 425 projects with a total value of $5,472,383,138 that Reed Construction Data Building Reports reported on Tuesday.
$60,000,000 Kelowna BC CANCELLED/ DEFERRED
WASTEWATER TREATMENT PLANT UPGRADES
$45,000,000 Grande Prairie AB Tenders
$30,000,000 West Vancouver BC Tenders
| CURRENT STORIES |
- High School Construction
- Victoria bridge inches closer to construction
- Collapse injures worker at Commonwealth Stadium
- Panel appointed to oversee hearings into B.C. mine project
- Bockstael celebrates 100 years
- More work needed to protect flaggers
- Co-founder of ATCO announces his intention to step down as chair
- SNC-Lavalin hit with $1.5 billion class action lawsuit
- PST returns to British Columbia
- Where does labour law stand on ladder safety?
- Construction continues on the MaRS Centre Phase II in Toronto
- Bending Lake Iron Ore pushes ahead with mining plans
- Reserve Properties continues plans for 109OZ condos in Toronto
- Ontario courts rule against owners rejecting low bids using undisclosed criteria
- Westray disaster 20th anniversary a call to safety action
- Dirt moves as Saskatchewan announces highway work
- Worker hurt in dressing room ceiling collapse at Edmonton stadium
- IBI Group raises $40.5 million from stock issue
- Plazacorp to spend $12.2 million on retail property development in 2012
- Ottawa to proceed with preliminary Lansdowne Park construction work, short-lists PCL, EllisDon and Pomerleau
- VIDEO: Highlights from the May 17 Daily Commercial News
- VIDEO: Common ladder safety errors in construction
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- Economic Nuggets - May 15, 2012 (May 14, 2012)
- Canada Rode a Second Consecutive Month of Strong Job Gains in April (May 11, 2012)
- U.S. Employment Rose by a Mediocre 115,000 in April (May 4, 2012)
- More









