JOC ARCHIVES

LATEST NEWS  Trade Contracting

October 17, 2012

Concerns over tender closings

Procurement Perspectives | Stephen Bauld

My conversations with contractors over the past several months suggest growing concerns over tender closings.

The process related to government procurement, and the closing of construction tenders can be very complicated. The period between the publication of the tender or RFP (Request for Proposals) Notice and the closing of the tender or RFP is known as the bid period.

Since the intent of a tender is for the suppliers, or contractors, to bring forward bids or proposals, the extent of the contract between the customer and the supplier is relatively limited, compared to what takes place in a negotiated contract.

Stephen Bauld

Procurement Perspectives

Stephen Bauld

The bidding process has its own unique risks, completely distinct from those associated with the overall contracting process, which must be understood and provided for just as in the case of any other contract related risk.

The bid period should be sufficiently long to allow bidders a reasonable time to prepare and submit their bids.

For most municipalities, the time allowed will range from 15 to 30 calendar days. However, the specific time allowed will reflect a range of considerations in relation to the proposed procurement, such as:

the degree of urgency;

the complexity of transaction and supply to be made;

whether it is necessary to allow for discussions with prospective subcontractors or any other suppliers;

the geographic distribution of prospective bidders; and whether any testing is required before the bids are made.

The provision of samples is atypical, and usually is required only when the characteristics of the product cannot be described adequately in the specification or purchase description.

For instance, the use of bid samples would be appropriate for products that must be suitable from the standpoint of balance, facility of use, general “feel” colour, pattern, or other characteristics that cannot be described in the specifications.

In some cases it may be considered advantageous to hold a pre-bid meeting with prospective bidders.

Such meetings are often used in a complex acquisition, as a means of briefing prospective bidders and explaining complicated specifications and requirements to them as early as possible after the invitation has been issued and before the bids are opened.

Care must be taken in relation to such meetings, to protect all parties concerned.

The municipality should have a designated speaker who will handle most of the discussion. The individual concerned must have a commanding knowledge of the purchasing project: if a project management system is in place, the ideal speaker would the project sponsor.

Other members of the internal team should speak with respect to issues only within their respective areas of expertise. Even so, the purpose of any such meeting is constructive dialogue.

Consequently artificial constraints should not be imposed. As much as possible, a record should be taken of all questions raised.

After the meeting, a formal reply should be sent to all prospective bidders. In government procurement contracts all bidders must receive the same information.

Any additional information related to the original contract should be issued in the form of a proper addendum to the RFP or tender. A meeting alone should not be used as a substitute for an addendum, in view of the risk of unrecorded remarks and ambiguous comments.

Generally, addenda are issued where it becomes necessary to make changes in quantity, specifications, delivery schedules, opening dates, or to correct a defective or ambiguous invitation.

The effect of any such addendum is to amend the terms and conditions of the tender or RFP, including the specifications, to the extent provided. The fact that a prospective change was mentioned at a pre-bid meeting does not relieve the necessity for issuing an amendment.

Stephen Bauld, Canada's leading expert on government procurement, is a member of the Daily Commercial News editorial advisory board. He can be reached at stephenbauld@bell.blackberry.net.

Print | Comment

MOST POPULAR STORIES
TODAY’S TOP CONSTRUCTION PROJECTS

These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.

LRT EXTENSIONS

$1,000,000,000 Edmonton AB Prebid

HOSPITAL ADDN, ALTS

$220,000,000 Medicine Hat AB Negotiated

AGRICULTURAL EXHIBITION EXPANSION

$50,000,000 Calgary AB Prebid

Daily Top 10

CURRENT STORIES
ALEX’S ECONOMICS BLOG

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.

TODAY’S TOP JOBS

Journeyman Plumber
Ontario-Cambridge

Finishing Superintendent
Ontario-Concord

Construction Project Manager for Heavy Civil Construction
Alberta-Edmonton

Construction Project Coordinator for Heavy Civil Construction
Alberta-Fort McMurray

Site Superintendent
Ontario-Concord

Estimator
Ontario-Brantford

HVAC Mechanic
British Columbia-Burnaby

SALES REPRESENTATIVE
Ontario-Toronto

Service Technician, Mechanic / Electrician
Ontario-Mississauga

Estimator
Ontario-Toronto

More jobs 

myJobsite.ca

Your gateway to
the top careers
in construction
and design