Victoria's historic bridge will be replaced
CITY OF VICTORIA
The new Johnson Street Bridge is scheduled for completion in March 2016. PCL Constructors Westcoast Inc. is the general contractor.
PCL Constructors Westcoast has been awarded a $63 million fixed-price contract by the City of Victoria, B.C. for the construction of the new Johnson Street Bridge.
“This is an important milestone in the life of this project,” noted Mayor Dean Fortin.
“This fixed price contract meets the design, project budget and timelines, and allows us to move forward with confidence on a project that will vastly improve cycling, walking and driving options to and from the downtown for generations.”
PCL was awarded the contract following a competitive process which included three teams each with a lead proponent and sub-contractors.
PCL will be working with MMM Group Ltd. which will act as project manager and prime consultant.
MMM Group has been the primary engineering consultant since 2009 and will continue to provide all professional engineering services through to the completion of the project.
The three shortlisted teams were led by PCL Constructors Westcoast Inc., Peter Kiewit Infrastructure Co. and WCC Construction Canada, ULC respectively.
During the procurement process, proponents were invited to propose measures that could reduce costs or risks, and minimize impacts during construction.
The fixed price contract includes the following six design features based on the input of all three firms.
Reducing the size of the east-side pier building, housing the bridge mechanism, and reduction of the size of the counterweight;
Using hydraulic motors, placed under the big wheels, to power the lift mechanism;
Simplifying the angled geometry of the west-side bridge pier;
Simplifying the tapering trusses of the bridge to require less welding;
Using concrete approach spans rather than steel; and
A concrete multi<0x2010>use trail overpass rather than steel.
The City of Victoria said these changes will help ensure that the contract is within the approved construction budget.
In December 2011, Victoria residents voted in favour of the city borrowing $50 million dollars to replace the 86-year-old Johnson Street Bridge, with a new rolling bascule bridge.
More than 16,000 residents voted in the referendum and it passed with 60 per cent voting in favour.
At the time, the bridge replacement was estimated to cost $77 million, which would have been the largest capital project in Victoria’s history.
City council later voted to increase the estimated cost of replacing the bridge to $92.8 million.
The Government of Canada is providing up to $37.5 million in funding, including $21 million from the Building Canada Fund and $16.5 million through Canada’s Gas Tax Fund.
The remaining bridge replacement costs are funded by the city through reallocated capital budgets and electoral approved borrowing.
According to the Times Colonist, two Victoria city councillors who voted against the deal, Lisa Helps and Ben Isitt, are concerned about the cost escalation.
They argue that the $2.8 million contingency fund is not large enough to cover potential risks.
This makes the contingency fund only 4.4 per cent of the construction budget, but 10-20 per cent is typical.
The Johnson Street Bridge project involves the construction of three vehicle lanes, on-road bike lanes, a multi-use trail for pedestrians and cyclists, and a pedestrian deck on the south side.
Construction of the new bridge is expected to begin this summer and generate about 900 jobs.
The project is expected to be fully completed by March 2016.
The contract includes decommissioning of the old bridge structure once the new bridge is complete.
It also includes the construction of improved road alignments and traffic calming features on both sides of the bridge, installation of a signal controlled intersection at Harbour and Esquimalt roads, widened sidewalks and pathways leading to the bridge with links to existing and future pathways and trails, public viewing and plazas areas on the east and west sides, and landscaping.
In addition, PCL will also build a retaining wall on the city’s adjacent property on Harbour Road to support an approach road beside the city-owned lot, which is outside the scope of the original contract.
The original Johnson Street Bridge has significant heritage value as its unique bascule bridge system was created by Joseph Strauss, one of the most famous bridge designers in the world.
The bridge was completed in 1924 at a cost of $918,000 and is one of the few bascule bridges left in North America.
If you would like to see building reports for the Johnson Street Bridge, please click here, here, and here.
CITY OF VICTORIA
| MOST POPULAR STORIES |
| TODAY’S TOP CONSTRUCTION PROJECTS |
These projects have been selected from 316 projects with a total value of $2,787,806,637 that Reed Construction Data Building Reports reported on Friday.
$1,000,000,000 Edmonton AB Prebid
$220,000,000 Medicine Hat AB Negotiated
AGRICULTURAL EXHIBITION EXPANSION
$50,000,000 Calgary AB Prebid
| CURRENT STORIES |
- Construction Site Arson
- Historic church renovation reaches new heights
- Hiring of foreign workers for hospital project outrages union
- Festival of Architecture hits Halifax
- Winnipeg Southwest Transitway wins award
- Vendor performance is key measurement
- NDP leader spoke to police about corruption
- Big contract down under for ATCO Structures
- RFQ issued for Kamloops hospital project
- VIDEO: Economic Update May 21, 2013
- VIDEO: Competing in the trades
- New ETFO headquarters a benchmark design
- Viana steps up to rebuild burnt down playground
- Random drug testing about site safety, says expert
- Trying to define the “lowest price”
- High job vacancy rates for small business
- Minto to assist in zero energy housing project
| ALEX’S ECONOMICS BLOG |

Reed Construction Data Canada’s Chief Economist Alex Carrick discusses current developments in the North American economic environment with emphasis on the construction industry.
- An Overview of Prices and Sales in the Diverging U.S. and Canadian Housing Markets (April 25, 2013)
- Canada’s Precarious Dependence on the Commodity Price Super-Cycle (April 22, 2013)
- Twenty major upcoming residential and transportation terminal construction projects - April 2013 (April 15, 2013)
- More