MINE MILL BLDG & RELATED FACILITIES Proj: 9134373-4
Thompson-Nicola RD, BC DEFERRED
Ajax Mine (Abacus Mining & Exploration), 10 Km SW of Kamloops
$450,000,000 est
Note: The project is currently in a pre-application stage with the environmental assessment process. The draft application requirements are currently under review by the BC Environmental Assessment office and the Federal Canadian Environmental Assessment office. The owner is also in discussions with First Nations groups and the general public. No movement anticipated on this until 2014. Update in early 2014. For geneneral information go to the project website: www.ajaxmine.ca.
Total capital budget is $535 million. Stantec Consulting Ltd are the Air Quality & Noise Consultants.
Project:development of a new copper & gold mine with a production capacity of 21.9 million tonnes of ore per year; utilizing a combined in-pit & out-pit gyratory primary crusher system; copper & gold to be recoverd in concentrate through a convetional flotation circuit; use of restored & expanded mine components from previous operations are expected to be utilized to the fullest extent possible. The mine components are: use of open-pit method, processing plant, thickening tailings plant, tailings storage facility, waste rock management facilities, water management facilities, road & bridge upgrades, new access & haul roads, borrow sources, transmission line & transformer upgrades, explosives storage facility, water supply including pumphouse upgrades, process & potable water system, concentrate storage & shipping area, & concentrate transport to Port of Vancouver.
Scope:250,000 square feet; 8 structures
Development:New
Category:Processing plants; Warehouse, storage bldgs; Misc industrial bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Coordinator Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other bldg designer Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mining eng services Complete information is available to subscribers. Click HERE to find out how to subscribe.
Environmental cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Apr 13, 2011. Last report Fri Jul 27, 2012.