UNDERWATER POWER LINES Proj: 9118296-6
Province of Ontario, ON PREPARING PLANS
Champlain Hudson Power Express, 65 km north of the Canadian border
$3,800,000,000 est
Note: Owner anticipates receiving Public Service Commission certificate regarding public hearings and Draft Environmental Impact Statement in 2013. Design is underway in-house at the owner. Further update fall 2013.
/www.chpexpress.com /www.transmissiondevelopers.com.
Project:proposed construction of an underwater transmission project beginning north of the Canadian border and running 596 km along the botton of Lake Champlain, down the bed of the Hudson River, into New York City, and under the Long Island Sound into Connecticut. The project will involve buried HVdc underwater and underground cable and will be installed using low-impact water jet technology.
Development:Engineering
Category:Elect power, engineering; Communications, distribution; Misc engineering
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed May 05, 2010. Last report Thu Feb 28, 2013.
This report Tue Jun 04, 2013.