WIND FARM Proj: 9170453-9
Souris, Kings County PE SUB AWARDS
Hermanville/Clearspring, 10 km north of Souris, between Hwy 305 and Hwy 306, C0A 2B0
$60,000,000 est
Start: May, 2013 Complete: November, 2013
Project:development of a 30 MW wind farm for domestic consumption. Project will consist of installations of 10 Acciona AW-3000/116 T92 Turbines, overhead and underground distribution lines, a 30 MVA set-up transformer and a service road network. Project also includes design/build construction of a 4,000 sq ft operations and maintenance building north of the access road off of Hwy 305.
Scope:10 structures
Development:Engineering
Category:Elect power, engineering; Misc industrial bldgs; Bridges
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Site work cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural trades cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Foundation cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Const manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Environmental cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner's representative Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Dec 27, 2012. Last report Wed Jun 19, 2013.
This report Fri Oct 18, 2013.