WATER STORAGE RESERVOIR AND WATER INTAKE Contractor's representative Proj: 9166812-3
Red Earth 29, Division No 14 SK AWARD
Red Earth First Nation Thu Oct 18, 2012 14:00
$1,000,000 est
Start: November, 2012 Complete: May, 2013
Note: Information regarding results not to be released for publication. Contact Bullée Consulting Ltd for tender results.
Project:The work includes: 1- Construction of a 213,000 m3 raw water storage reservoir with approximately 35,000 m3 common excavation and 70,000 m3 of imported fill; 2- Scarification and compaction of proposed floor at a depth of 300 mm; 3- Installation of manhole connecting drains, fencing and miscellaneous work; 4- Supply and installation of packaged aeration system; 5- Supply and installation of an intake system complete with control structure, fish screens and connection to existing system; 6- Provision of roads for ingress and egress to the locations of all work required. 7- Clean up of site; 8- Repair of defects for one year after completion of the work.
Development:Engineering
Category:Sewage & Water plants
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Contractor's representative Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Tue Oct 02, 2012. Last report Thu Oct 11, 2012.
This report Thu Nov 15, 2012.