SECONDARY SCHOOL, RECREATIONAL BUILDING Proj: 9089001-20
Regina, Division No 6 SK WORKING DRAWINGS
North Central Shared Facility - Phase 1, 7 Ave & Athol St, Elphinstone St, S4R
$30,000,000 est
Start: June, 2014 Complete: June, 2016
Note: Working drawings are underway. Scope of work is being reviewed. Completion of working drawings is anticipated April, 2014. Schedules for tender for general contractor will be determined early summer, 2014. Construction schedules will be set summer, 2014.
The owners listed on this report are contributing members of a development consortium for the project. Project Coordinator - Allen Lefebvre, Phone: 306-537-2978. www.northcentralsharedfacility.ca.
Project:concrete foundation, cast-in-place concrete structural frame, structural steel frame, fuel fired heating system, in-floor radiant heating system; air handling units; construction of a shared facility. Project will include spaces for a library, cafe, information technology centre, gymnasium, daycare, classroom and administrative spaces. The project will be certified under the Leadership in Energy and Environmental Design (LEED) Green Building Program with a LEED Silver rating.
Scope:103,000 square feet; 2 storeys; 1 storey below grade
Development:New
Category:Educational bldgs; Recreational bldgs; Public bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Landscape architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Environmental cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Fri Aug 29, 2008. Last report Mon Sep 09, 2013.
This report Fri Jan 17, 2014.