WASTEWATER TREATMENT PLANT Proj: 9168859-4
St-Alphonse-Rodriguez, Matawinie, comté QC NEGOTIATED/PLANNING
municipalité de St-Alphonse-Rodriguez, J0K
$19,500,000 est
Start: 2013 Complete: January, 2016
Note: Request for proposals from professional consulting firms (fccq 801-2012) closed at 10:00 Quebec time December 11, 2012 at the owner and has been awarded. Consultants will assist the municipality in the selection of consulting engineering firms for the project plans and specifications preparation and the project management. Preparation of documents necessary for engineering firm selection is ongoing at the consultant. Schedules for design, tender for the general contractor and construction have yet to be determined. Further update summer 2013.
Project:construction of a wastewater treatment system serving a part of the municipality. The scope of the project includes construction of an aqueduct and sewage system and wastewater treatment facilities.
Development:Engineering
Category:Sewage & Water plants
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Project manager Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Nov 15, 2012. Last report Thu Dec 13, 2012.
This report Thu Jan 24, 2013.