ARENA ALTS Proj: 9161016-5
Montréal, Communauté urbaine de Montréal, comté QC PREPARING PLANS
Aréna Roberto-Luongo, 7755 rue Colbert, H1R 2B6
$7,100,000 est
Start: May, 2014 Complete: May, 2015
Note: Preliminary plans are being finalized. Working drawings are anticipated late summer/early fall 2013. Tender for the general contractor is preliminarily slated for mid-/late fall 2013.
Project:proposed environmentally friendly upgrades and repairs to the arena building and its systems. The project will aim for certification under the Leadership in energy and environmental design (LEED) green building rating system.
Development:Alterations
Category:Recreational bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Structural cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Mechanical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Electrical cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Jun 28, 2012. Last report Mon Jan 21, 2013.
This report Wed May 15, 2013.