| Note: | Project is currently in engineering design and equipment procurement phase. Owner is currently in discussions for long-term financing. Installation and construction schedules to be confirmed in spring 2013. Further update at that time. |
| Project: | construction of a bioenergy facility in Mackenzie which is expected to generate approximately 230 gigawatt hours (GWh) of net energy per year, enough to power 24,000 BC homes annually. |
| Development: | Engineering |
| Category: | Elect power, building; Elect power, engineering |
| Owner | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Gen cont | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Other bldg designer | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Other cons eng serv | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|