OFFICE BUILDING ALTS Proj: 9171112-3
Québec, Communauté urbaine de Québec, comté QC CONTEMPLATED
Nouvelles Casernes, rue de l'Arsenal, G1R
$18,700,000 est
Start: 2014 Complete: 2019
Note: Request for proposals (RFP) from professional consulting firms (A13-0104) closed at 14:00 January 31, 2013 at the owner and has been awarded. Consultants are responsible for a feasibility study preparation and the project scope determination. Feasibility study preparation is underway. Study report presentation to the owner is anticipated late spring/early summer 2013. Further project development schedules will be determined based on the study results.
Project:upgrades and alterations to the Nouvelles Casernes seven-section heritage building to transform it into an administrative or meeting-office building. The scope of the project includes upgrades and repairs to the exterior envelope, interior alterations and upgrades to electrical and mechanical systems of the building.
Scope:2 storeys; 1 storey below grade; 7 units
Development:Alterations
Category:Government offices
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other cons eng serv Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Jan 16, 2013. Last report Tue Feb 05, 2013.
This report Mon Feb 25, 2013.