| Note: | Detailed design is underway. Working drawings are expected to begin late spring/early summer, 2013. Tender for general contractor is anticipated June/July 2013. Construction start is expected summer 2013. |
| Project: | renovation of the endoscopy unit and intensive care unit. This project will be built using Lean construction methods. |
| Development: | Alterations |
| Category: | Hospitals |
| Owner | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|
| Architect | Complete information is available to subscribers. Click HERE to find out how to subscribe.
|