ROADWORK, SHORE LINE ALTS Proj: 9032199-19
Gatineau, Communauté urbaine de l'Outaouais, comté QC PREPARING PLANS
rue Jacques-Cartier, Pont Lady Aberdeen et rue Saint-Louis, J8T
$32,000,000 est
Note: Geotechnical study is completed by the consultants. Preliminary design is underway. Tender for general contractor and construction timelines will be determined once government approvals are in place. Construction will last two years. Further updates in fall, 2013.
Project:roadwork; streetscaping; pedestrian paths; renaturalization of the shoreline; landscaping.
Development:Engineering
Category:Roads; Marine eng
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Civil cons eng Complete information is available to subscribers. Click HERE to find out how to subscribe.
Geotechnical cons Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Tue Feb 14, 2006. Last report Thu Jan 17, 2013.
This report Fri Apr 19, 2013.