OIL SANDS Proj: 9121146-5
Cold Lake, Division No 12 AB WORKING DRAWINGS
Foster Creek Oil Sands SAGD Project - Phase H, Foster Creek, Alberta
$1,000,000,000 est
Start: June, 2014 Complete: January, 2016
Note: Detailed engineering is underway. Ground preparation is complete. Site preparaton, tender and construction schedules to be confirmed in summer 2013. Further update at that time.
Project:proposed construction of an oil sands plant which will have an expected production of 210,000 barrels of oil per day using steam-assisted gravity drainage (SAGD).
Development:Engineering
Category:Oil refineries
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other bldg designer Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Wed Jun 23, 2010. Last report Mon Mar 26, 2012.
This report Wed Jul 11, 2012.