ELECTRIC TRANSMISSION LINES Proj: 9135954-5
Division No 11, AB NEGOTIATED/START
Heartland Transmission Project, northeast of Fort Saskatchewan
$580,000,000 est
Start: January, 2012 Complete: September, 2013
Note: Site preparation and construction activities are underway along the transmission line route.
AltaLink and Epcor are partnering on this project.
Project:construction of a 500-kV double circuit transmission line which will connect the Heartland region (northeast of Fort Saskatchewan) to existing 500 kV facilities.
Development:Engineering
Category:Elect power, engineering
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Gen cont Complete information is available to subscribers. Click HERE to find out how to subscribe.
Other bldg designer Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Tue May 10, 2011. Last report Tue Jan 31, 2012.
This report Tue Jun 26, 2012.