COURT HOUSE ALTS Proj: 9160445-4
Montréal, Communauté urbaine de Montréal, comté QC WORKING DRAWINGS
Cour d'appel du Québec, 100 rue Notre-Dame Est, H2Y 1C1
$8,700,000 est
Start: July, 2013 Complete: May, 2015
Note: Working drawings are ongoing. Tender for the general contractor is anticipated late spring/early summer 2013.
Project:proposed construction works to replace historic windows and repair the heritage building masonry.
Development:Alterations
Category:Defence, law enforcement bldgs
Owner Complete information is available to subscribers. Click HERE to find out how to subscribe.
Architect Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
Consultant Complete information is available to subscribers. Click HERE to find out how to subscribe.
First report Thu Jun 21, 2012. Last report Fri Aug 03, 2012.
This report Wed Mar 20, 2013.